For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the excavated volume, the volume taken by the foundations, the fill depth and your compaction allowance, and get the loose fill to bring in, the number of layers and the truckloads.
Worked example
With the calculator’s starting values:
| Excavated volume | 180 m³ |
|---|---|
| Volume of foundations and structure below ground | 35 m³ |
| Total fill depth | 1.5 m |
| Compacted layer thickness | 200 mm |
| Compaction allowance | 20 % |
| Truck capacity (loose) | 20 m³ |
| Loose fill needed | 174 m³ |
|---|---|
| Compacted backfill | 145 m³ |
| Number of layers | 8 layers |
| Truckloads of fill | 9 trucks |
| Loose fill in cubic feet | 6,145 cft |
How it is calculated
Compacted backfill = excavated volume − volume of the structure below ground
Loose fill needed = compacted backfill × (1 + compaction allowance)
Layers = total fill depth ÷ compacted layer thickness, rounded up
Truckloads = loose fill ÷ truck capacity, rounded up
The structure below ground includes footings, blinding, tie beams, column necks and any slab or wall set into the excavation. The compaction allowance covers the extra loose material needed to reach the specified density; 20% is only an example.
Backfilling in the UAE
On sites in Dubai, Sharjah, Abu Dhabi and Ajman backfill is usually placed and compacted in layers to the density in the specification, with field density tests before the next layer. Whether you can reuse the excavated sand or must import approved fill depends on the specification and the soil, so check with the consultant before you plan the quantities.
Questions
Can I reuse the excavated soil?
Often, if it meets the specification. Compare the loose fill needed here with the loose volume you dug out to see whether you have a surplus or need to import.
Why is more loose fill needed than the hole?
Fill is delivered loose and loses volume when it is compacted, so you need more loose material than the compacted space it fills.