For contractors, QS and facility managers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the floor area and, for the primer, body coat and top coat, the consumption or coverage from the data sheet, the number of coats and the kit size, and get the material and kits to buy.
Worked example
With the calculator’s starting values:
| Floor area | 100 m² |
|---|---|
| Data sheet gives | Consumption per m² |
| Material and kits measured in | kg |
| Primer consumption per coat | 0.3 kg or L per m² |
| Primer coats | 1 |
| Primer kit size | 10 |
| Body coat consumption per coat | 0.4 kg or L per m² |
| Body coats | 1 |
| Body coat kit size | 20 |
| Top coat consumption per coat | 0.3 kg or L per m² |
| Top coats | 1 |
| Top coat kit size | 20 |
| Wastage | 10 % |
| Kits in total | 9 kits |
|---|---|
| Primer | 33 kg |
| Primer kits | 4 kits of 10 kg |
| Body coat | 44 kg |
| Body coat kits | 3 kits of 20 kg |
| Top coat | 33 kg |
| Top coat kits | 2 kits of 20 kg |
How it is calculated
Each layer = area × coats × consumption per coat × (1 + wastage)
With coverage instead: consumption per coat = 1 ÷ coverage
Kits = layer quantity ÷ kit size, rounded up
Kits in total = primer kits + body coat kits + top coat kits
Epoxy data sheets give either a consumption (kg or litres per m² per coat) or a coverage (m² per kg or litre). Choose the one your data sheet uses. The defaults are only examples. A self-smoothing or trowelled system can use much more per coat than a roller-applied coating, so use the figures for the exact system and thickness specified.
Kits and part kits
Epoxy is sold as a kit of base and hardener in a fixed ratio, and the whole kit is normally mixed at once. The calculator rounds each layer up to whole kits, so expect some material left over. Kit sizes differ between products and between primer and finish coats, so enter the sizes on the products you will buy.
Epoxy flooring in the UAE
Epoxy floors are common in warehouses, car parks, kitchens, workshops and plant rooms in Dubai, Sharjah, Abu Dhabi and Ajman. Pot life and recoat times on the data sheet are stated at a set temperature and shorten in the heat, so mix only what the crew can apply in time. The concrete or screed must be prepared and dry enough for the system, so check the moisture limits and preparation on the data sheet before you start.
Questions
How many kits for 100 m²?
With the example figures above and 10% wastage: 33 kg of primer (4 kits of 10 kg), 44 kg of body coat (3 kits of 20 kg) and 33 kg of top coat (2 kits of 20 kg), so 9 kits in total. Your system will differ.
Do I need a self-levelling layer first?
Only if the floor is too uneven for the system. Use the self-levelling compound calculator if the specification calls for one.