For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman waterproofing a roof, balcony or bathroom: enter the size in metres, the upturn height and the product’s consumption to get packs of coating and primer.

Waterproofing coating8 packs of 20 kg

Worked example

With the calculator’s starting values:

Inputs
Area inputRoof or room size
Length10 m
Width8 m
Upturn height at walls300 mm
Consumption per coat0.75 kg/m²
Number of coats2 coats
Pack size20 kg
PrimerInclude primer
Primer use0.2 L/m²
Primer pack size18 L
Wastage10 %
Results
Waterproofing coating8 packs of 20 kg
Coating quantity149.8 kg
Primer2 packs of 18 L

How it is calculated

Area = length × width + 2 × (length + width) × upturn height

Coating = area × consumption per coat × coats × (1 + wastage)

Packs = coating ÷ pack size, rounded up

Primer = area × primer use × (1 + wastage)

Upturns and details

The coating usually runs up walls and parapets to the height the specification gives, so the calculator adds that strip around the full perimeter. Drains, pipes, corners and joints often need reinforcing fabric or extra coats; allow for them as the system data sheet sets out.

Defaults you can change

0.75 kg/m² per coat, 2 coats and 0.2 L/m² of primer are example figures only. Cementitious, polyurethane, acrylic and bitumen coatings all differ, so take the consumption, coats and pack sizes from the product data sheet.

Waterproofing in the UAE

Flat concrete roofs, balconies, bathrooms and other wet areas are routinely waterproofed in Dubai, Sharjah, Abu Dhabi and Ajman. Liquid coatings are sold in pails and drums by weight or volume, so turn the area into kilograms or litres before you compare quotes. Strong sun and heat on roofs shorten working and curing times, so follow the data sheet for application temperature and check the system against the consultant’s specification.

Questions

My data sheet gives litres, not kg. Does it still work?

Yes. Enter the consumption in L/m² and the pack size in litres. The arithmetic is the same, so the pack count is right; read the kg figures as litres.

How many coats do I need?

Follow the data sheet and the specification. The number of coats is set by the dry film thickness the system needs.

Do the quantities include VAT?

No. The calculator gives quantities only. Building materials in the UAE carry 5% VAT, so check whether a supplier’s quote is before or after VAT.