Worked example
With the calculator’s starting values:
| Kerb length | 50 m |
|---|---|
| Kerb unit length | 500 mm |
| Joint width | 5 mm |
| Bed width | 300 mm |
| Bed thickness | 150 mm |
| Back haunch height | 150 mm |
| Back haunch width | 150 mm |
| Kerb wastage | 3 % |
| Concrete wastage | 5 % |
| Kerbstones | 102 pieces |
|---|---|
| Concrete for bed and haunch | 2.95 m³ |
How it is calculated
Kerbs = kerb length ÷ (unit length + joint) × (1 + wastage), rounded up
Concrete section = bed width × bed thickness + ½ × haunch height × haunch width
Concrete = kerb length × section × (1 + wastage)
cft = m³ × 35.3147
Curves and dropped kerbs
Tight curves need radius kerbs, and driveway entrances often use dropped or transition kerbs. Count these separately from the straight run and take their lengths off the drawings.
Defaults you can change
The 5 mm joint, 300 × 150 mm bed, 150 × 150 mm haunch and the wastage figures are example values. Use the kerb detail on the drawings.
Kerbstones in the UAE
Precast concrete kerbs are used along roads, car parks, villa driveways and landscaped areas in Dubai, Sharjah, Abu Dhabi and Ajman. They are sold by the piece and delivered on pallets, and the bed and haunch concrete is often ordered as ready-mix by the m³. Check kerb type, size and bedding details against the approved drawings and the consultant’s specification.
Questions
How many 500 mm kerbs are in a metre?
Two with tight joints. With a 5 mm joint each kerb takes 0.505 m, so 100 kerbs cover 50.5 m.
How do I convert m³ to cft?
Multiply by 35.3147. 1 m³ is 35.3147 cft.
Do the quantities include VAT?
No. The calculator gives quantities only. Building materials in the UAE carry 5% VAT, so check whether a supplier’s quote is before or after VAT.