Stair Calculator UAE: Riser Height, Going and Number of Steps

Enter the floor to floor height, the maximum riser and the going and get the number of risers and treads, the exact riser height, the pitch and the 2R + G check. For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman laying out staircases in villas and buildings, in mm.

Number of risers19 risers

Worked example

With the calculator’s starting values:

Inputs
Floor to floor height3,200 mm
Maximum riser height175 mm
Going (tread depth)275 mm
Results
Number of risers19 risers
Riser height168.4 mm
Number of treads18 treads
Total going on plan4.95 m
Pitch31.5 °
2R + G check612 mm
Sloping length along nosings5.8 m

How it is calculated

Risers = floor to floor height ÷ maximum riser, rounded up

Riser height = floor to floor height ÷ risers

Treads = risers − 1 (the top floor is the last step)

Total going = treads × going

Pitch = arctan(riser ÷ going)

Sloping length = treads × √(riser² + going²)

The 2R + G check

Twice the riser plus the going is a common comfort check. UK guidance (Approved Document K) asks for 2R + G between 550 and 700 mm. Use the rule in the code or specification for your project.

Defaults you can change

The 175 mm maximum riser and 275 mm going are example values. Enter the limits from your drawings or the code that applies.

Staircases in the UAE

Most staircases in villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman are cast in concrete and then finished with marble, granite or tiles. Work out the riser from the finished floor levels, not the structural slab levels, and allow for the finish on each tread so every step comes out equal. Check riser, going and headroom against the approved drawings.

Questions

Why is the number of treads one less than the risers?

The top riser lands on the upper floor, so that floor acts as the last tread.

Should I measure from slab or finished floor?

From finished floor to finished floor. If the screed or tile build-up differs between floors, the first or last step will be a different height.

Does the going include the nosing?

No. Going is measured on plan from one nosing to the next, so the overhang of the nosing is not added.