Enter the floor to floor height, the maximum riser and the going and get the number of risers and treads, the exact riser height, the pitch and the 2R + G check. For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman laying out staircases in villas and buildings, in mm.
Worked example
With the calculator’s starting values:
| Floor to floor height | 3,200 mm |
|---|---|
| Maximum riser height | 175 mm |
| Going (tread depth) | 275 mm |
| Number of risers | 19 risers |
|---|---|
| Riser height | 168.4 mm |
| Number of treads | 18 treads |
| Total going on plan | 4.95 m |
| Pitch | 31.5 ° |
| 2R + G check | 612 mm |
| Sloping length along nosings | 5.8 m |
How it is calculated
Risers = floor to floor height ÷ maximum riser, rounded up
Riser height = floor to floor height ÷ risers
Treads = risers − 1 (the top floor is the last step)
Total going = treads × going
Pitch = arctan(riser ÷ going)
Sloping length = treads × √(riser² + going²)
The 2R + G check
Twice the riser plus the going is a common comfort check. UK guidance (Approved Document K) asks for 2R + G between 550 and 700 mm. Use the rule in the code or specification for your project.
Defaults you can change
The 175 mm maximum riser and 275 mm going are example values. Enter the limits from your drawings or the code that applies.
Staircases in the UAE
Most staircases in villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman are cast in concrete and then finished with marble, granite or tiles. Work out the riser from the finished floor levels, not the structural slab levels, and allow for the finish on each tread so every step comes out equal. Check riser, going and headroom against the approved drawings.
Questions
Why is the number of treads one less than the risers?
The top riser lands on the upper floor, so that floor acts as the last tread.
Should I measure from slab or finished floor?
From finished floor to finished floor. If the screed or tile build-up differs between floors, the first or last step will be a different height.
Does the going include the nosing?
No. Going is measured on plan from one nosing to the next, so the overhang of the nosing is not added.