For contractors, site engineers and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the quantity in m³, the bulking and loose density, and the truck body volume and payload, and get the number of tipper trips, the tonnes moved and how many working days it takes.
Worked example
With the calculator’s starting values:
| Quantity to move | 150 m³ |
|---|---|
| Bulking when loaded loose | 25 % |
| Loose density | 1.6 t/m³ |
| Truck body volume | 18 m³ |
| Allowed payload | 30 t |
| Trucks available | 2 |
| Trips per truck per day | 6 |
| Truck loads | 11 trips |
|---|---|
| Loose volume | 187.5 m³ |
| Weight | 300 t |
| Limited by | Body volume |
| Working days | 0.9 days |
| Average load per trip | 27.3 t |
How it is calculated
Loose volume = quantity × (1 + bulking)
Weight = loose volume × loose density
Trips by volume = loose volume ÷ truck body volume
Trips by weight = weight ÷ allowed payload
Truck loads = the larger of the two, rounded up
Working days = truck loads ÷ (trucks × trips per truck per day)
A truck is full when it reaches either its body volume or its payload, whichever comes first. Light material such as loose soil usually fills the body first; heavy material such as wet sand or aggregate can reach the payload first.
Defaults you can change
The 25% bulking, 1.6 t/m³ loose density, 18 m³ body and 30 t payload are example values only. Bulking and density change with the material and its moisture, and truck sizes vary, so use your supplier’s and haulier’s figures. Trips per day depend on the distance, traffic and loading time.
Truck loads in the UAE
Sand, aggregate and fill in Dubai, Sharjah, Abu Dhabi and Ajman are commonly delivered by tipper truck, and suppliers may quote per load, per tonne, per m³ or per cft. Work out your quantity in the same unit as the quote before you compare, and confirm the body size and allowed load with the haulier.
Questions
How do I convert m³ to cft?
Multiply by 35.3147. 1 m³ is 35.3147 cubic feet.
Why is the loose volume bigger than the volume I measured?
Dug or loaded material has more air in it than when it was in place or compacted, so it takes more room in the truck.
Should I add VAT to the transport?
In the UAE, VAT is charged at 5% where it applies. Ask your supplier whether the quote includes it.