For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Add a wastage allowance to a net quantity in m², m³, kg, pieces or 50 kg bags and round it to whole packs, find the net usable quantity in an order, or check the actual wastage % from what was used on site.
Worked example
With the calculator’s starting values:
| Calculation | Order quantity from net quantity |
|---|---|
| Unit | m² |
| Net quantity | 100 |
| Wastage allowance | 5 % |
| Pack or unit size | 0 (no rounding) |
| Quantity to order | 105 m² |
|---|---|
| Wastage quantity | 5 m² |
How it is calculated
Quantity to order = net quantity × (1 + wastage %)
Packs = quantity to order ÷ pack size, rounded up
Net usable quantity = quantity ordered ÷ (1 + wastage %)
Actual wastage % = (quantity used − net quantity) ÷ net quantity × 100
With the starting values, 100 m² × 1.05 = 105 m² to order, of which 5 m² is the wastage allowance.
Wastage on net or on the order
A wastage allowance is usually added to the net measured quantity, so 5% on 100 m² gives 105 m². The same 5 m² is only 4.76% of the 105 m² ordered, which is why the net mode divides by (1 + wastage %) instead of taking 5% off.
Defaults you can change
The 5% allowance is an example. Wastage depends on the material, the cutting, the layout and how it is handled on site, so use your own figure or the one in your estimate.
Material wastage in the UAE
In Dubai, Sharjah, Abu Dhabi and Ajman most materials are bought in fixed packs, such as 50 kg cement bags, boxes of tiles, pallets of blocks and 12 m rebar, so the order is rounded up to whole units after the wastage allowance. Enter the pack size to see the whole packs, and check the allowance against your estimate or the consultant’s specification.
Questions
What wastage percentage should I use?
There is no single figure. It depends on the material and the job, so use your own records or your estimate. Track the actual wastage with the third mode to improve the next estimate.
Why does 5% added become 4.76% of the order?
Because the wastage is the same quantity but the order is bigger than the net quantity. 5 ÷ 105 = 4.76%.
Can I use this for cement bags or tile boxes?
Yes. Choose the unit and enter the pack size, for example 1 for bags or the m² per box for tiles, and the order is rounded up to whole packs.