For UAE roofing and waterproofing contractors laying foam concrete for roof falls: enter the roof area in m², the average thickness and your mix per m³, and get the volume in m³, the 50 kg cement bags, the foaming agent and the added roof load.
Worked example
With the calculator’s starting values:
| Roof area | 150 m² |
|---|---|
| Average thickness | 100 mm |
| Cement per m³ | 300 kg |
| Foaming agent per m³ | 1 L |
| Dry density | 600 kg/m³ |
| Wastage | 5 % |
| Foam concrete volume | 15.75 m³ |
|---|---|
| Cement | 95 bags of 50 kg |
| Foaming agent | 15.8 L |
How it is calculated
Volume = roof area × average thickness × (1 + wastage)
Cement = volume × cement per m³; bags = kg ÷ 50
Foaming agent = volume × litres per m³
Added load = dry density × average thickness
For a roof laid to falls, the average thickness is the minimum thickness plus half the total fall. The screed to falls calculator works this out from the slope and run.
Defaults you can change
The 300 kg cement, 1 L foaming agent, 600 kg/m³ density and 5% wastage are example values only. Foam concrete mixes vary with the density you want, so use your mix design or the foam supplier’s data. The roof load row is a quick check; the structural engineer has the final word on what the slab can carry.
Foam concrete roofs in the UAE
Lightweight foam concrete is widely used on flat roofs in Dubai, Sharjah, Abu Dhabi and Ajman to form the falls to the drains and add some insulation without the weight of a sand-cement screed. It is normally laid between the roof slab and the waterproofing and protection layers, so follow the build-up in the consultant’s roof detail.
Questions
Is foam concrete lighter than screed?
Yes. Its density depends on the mix, but it is much lighter than a normal sand-cement screed, which is why it is used for thick roof falls.
Does foam concrete need waterproofing?
Yes. It is a fill and falls layer, not a waterproof layer, so a membrane or coating is still needed as the roof detail shows.
Can I order foam concrete by the m³?
Many contractors produce it on site with a foam generator, while some suppliers offer it pumped to the roof. Either way, the m³ result is the volume to plan for.