For contractors, QS and site managers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the quantity of work in m², m³, m or nos, the output per worker per day and the crew size, and get the man-days, crew working days, man-hours and calendar weeks.
Worked example
With the calculator’s starting values:
| Quantity of work | 500 |
|---|---|
| Unit | m² |
| Output per worker per day | 10 units |
| Workers in the crew | 4 |
| Working hours per day | 8 h |
| Working days per week | 6 days |
| Allowance for delays | 10 % |
| Crew working days | 14 days |
|---|---|
| Man-days | 55 man-days |
| Man-hours | 440 man-hours |
| Calendar weeks | 2.3 weeks |
How it is calculated
Man-days = quantity ÷ output per worker per day × (1 + allowance)
Crew working days = man-days ÷ workers, rounded up
Man-hours = man-days × working hours per day
Calendar weeks = crew working days ÷ working days per week
The output rate must be in the same unit as the quantity, for example m² of blockwork per mason per day. If a trade works in a gang, such as one mason with one helper, enter the output per gang and the number of gangs instead.
Defaults you can change
The output of 10 units per worker per day and the 10% allowance are example values only. Output depends on the trade, the drawings, access, heat and the crew, so use your own site records or your estimating rates.
Labour planning in the UAE
Many sites in Dubai, Sharjah, Abu Dhabi and Ajman work a six-day week, so that is the starting value here; change it to suit your site. From 15 June to 15 September the midday break stops outdoor work in the sun from 12:30 to 3 pm, so lower the working hours, and usually the daily output, for outdoor trades in summer.
Questions
What is the difference between man-days and crew days?
Man-days are the total days of one worker. Crew days are how long the job takes with the whole crew: man-days divided by the number of workers.
Does the summer midday break change the result?
It changes the inputs. Fewer working hours in the day usually means a lower output per worker, so enter the summer figures for outdoor work.
Can I use this for subcontractor programmes?
Yes, as a first check. Compare the crew days with the subcontractor’s programme and ask where the figures differ.