Labour Days Calculator UAE: Man-Days, Crew Days and Man-Hours

For contractors, QS and site managers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the quantity of work in m², m³, m or nos, the output per worker per day and the crew size, and get the man-days, crew working days, man-hours and calendar weeks.

Crew working days14 days

Worked example

With the calculator’s starting values:

Inputs
Quantity of work500
Unitm²
Output per worker per day10 units
Workers in the crew4
Working hours per day8 h
Working days per week6 days
Allowance for delays10 %
Results
Crew working days14 days
Man-days55 man-days
Man-hours440 man-hours
Calendar weeks2.3 weeks

How it is calculated

Man-days = quantity ÷ output per worker per day × (1 + allowance)

Crew working days = man-days ÷ workers, rounded up

Man-hours = man-days × working hours per day

Calendar weeks = crew working days ÷ working days per week

The output rate must be in the same unit as the quantity, for example m² of blockwork per mason per day. If a trade works in a gang, such as one mason with one helper, enter the output per gang and the number of gangs instead.

Defaults you can change

The output of 10 units per worker per day and the 10% allowance are example values only. Output depends on the trade, the drawings, access, heat and the crew, so use your own site records or your estimating rates.

Labour planning in the UAE

Many sites in Dubai, Sharjah, Abu Dhabi and Ajman work a six-day week, so that is the starting value here; change it to suit your site. From 15 June to 15 September the midday break stops outdoor work in the sun from 12:30 to 3 pm, so lower the working hours, and usually the daily output, for outdoor trades in summer.

Questions

What is the difference between man-days and crew days?

Man-days are the total days of one worker. Crew days are how long the job takes with the whole crew: man-days divided by the number of workers.

Does the summer midday break change the result?

It changes the inputs. Fewer working hours in the day usually means a lower output per worker, so enter the summer figures for outdoor work.

Can I use this for subcontractor programmes?

Yes, as a first check. Compare the crew days with the subcontractor’s programme and ask where the figures differ.