For contractors, site engineers and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the length and height of the face in metres with the bay length and lift height, and get the scaffold area in m² plus a count of standards, ledgers, transoms, base plates and boards for an independent scaffold.
Worked example
With the calculator’s starting values:
| Scaffold length along the face | 20 m |
|---|---|
| Height to the top working level | 9 m |
| Standards above the top platform | 1 m |
| Bay length | 2 m |
| Lift height | 2 m |
| Boarded platforms | 1 |
| Boards across each platform | 5 |
| Scaffold face area | 200 m² |
|---|---|
| Bays | 10 bays |
| Lifts | 5 lifts |
| Standards | 22 nos |
| Total length of standards | 220 m |
| Ledgers | 120 nos |
| Transoms | 55 nos |
| Base plates | 22 nos |
| Boards | 50 nos |
| Guardrails (main and intermediate) | 20 nos |
| Toe boards | 10 nos |
How it is calculated
Face area = length × (height + standards above the top platform)
Bays = length ÷ bay length, rounded up; lifts = height ÷ lift height, rounded up
Standards = 2 × (bays + 1), one inner and one outer per frame line; one base plate each
Ledgers = 2 × bays × (lifts + 1), inner and outer at the base and every lift
Transoms = (bays + 1) × lifts
Boards = bays × boards across × boarded platforms; guardrails = 2 × bays × platforms; toe boards = bays × platforms
The count is for one straight run of independent scaffold, one board length per bay. It leaves out bracing, ties, couplers, end guardrails, ladders or stair towers and intermediate transoms under the boards. Add these from the scaffold design.
Use it for planning, not design
Bay length, lift height, ties and bracing depend on the scaffold system, the load class and the wind on the building. A competent scaffold designer or supplier must set them, and the scaffold must be erected and inspected by competent people.
Scaffolding in the UAE
On sites in Dubai, Sharjah, Abu Dhabi and Ajman, scaffolding is usually hired from scaffolding companies and quoted by the square metre of face or by the component, so the area and counts here help you compare quotes. The main contractor’s safety plan and the consultant’s requirements apply. From 15 June to 15 September the midday break stops outdoor work in the sun from 12:30 to 3 pm, so plan erection hours around it.
Questions
Is the face area the same as the hire area?
Not always. Hire companies measure in different ways, so ask how the quote is measured before you compare.
Why are the lifts rounded up?
The scaffold must reach the top working level, so a part lift still needs a full set of ledgers and transoms.
Does this include the ties?
No. Tie spacing comes from the scaffold design and depends on the building, the cladding and the wind.