Block Calculator UAE: Blocks per Wall, Mortar and Cement

Enter the wall size and openings, choose the block, and get the number of blocks plus the mortar, cement bags and sand to lay them.

Blocks needed342 blocks

Worked example

With the calculator’s starting values:

Inputs
Wall length10 m
Wall height3 m
Openings to deduct2 m²
Block face (length × height)400 × 200 mm
Block thickness200 mm
Mortar joint10 mm
Mortar mix (cement : sand)1 : 4
Block wastage5 %
Results
Blocks needed342 blocks
Cement for mortar4 bags of 50 kg
Sand for mortar0.42 m³

How it is calculated

Blocks per m² = 1 ÷ [(block length + joint) × (block height + joint)]

Blocks = (wall area − openings) × blocks per m² × (1 + wastage)

Mortar = wall volume − volume taken by the blocks

Cement and sand = mortar × 1.33 dry factor, split by the mix ratio

With a 400 × 200 mm block and a 10 mm joint, each block covers 0.41 × 0.21 m, which gives 11.6 blocks per m².

Read the mortar figure carefully

The mortar result assumes a full mortar bed, as for solid blocks. Hollow blocks laid on their face shells use less, so treat the figure as an upper limit and go by your mason’s experience for hollow work. Cement uses 1,440 kg/m³ and 50 kg bags.

Blockwork in the UAE

Hollow and solid concrete blocks with a 400 × 200 mm face, in 100, 150 and 200 mm thicknesses, are widely used for walls in Dubai, Sharjah, Abu Dhabi and Ajman, and AAC blocks are used where a lighter wall is wanted. Blocks are sold per piece or per pallet, so turn your wall area into a block count before you compare quotes, and check the block type against your drawings and the consultant’s specification.

Questions

How many blocks are in 1 m² of wall?

11.6 for 400 × 200 mm blocks with 10 mm joints, 7.8 for 600 × 200 mm, and 6.3 for 600 × 250 mm. Thickness does not change the count, only the price and mortar.

Does block thickness change the number of blocks?

No. It changes the mortar volume and the block price. Use the thickness on your drawings.

What wastage should I allow?

5% is an example. Breakage in transport and cutting at corners and openings vary by job, so use your own figure.

Shopping Cart