Column Calculator UAE: Concrete, Main Bars and Ties

For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the column size, height and reinforcement, and get the concrete in m³ and cft, the main bars and ties, and the total steel weight.

Concrete to order2.42 m³

Worked example

With the calculator’s starting values:

Inputs
ShapeRectangular
Width300 mm
Depth600 mm
Height3.2 m
Number of columns4
Number of bars8
Bar diameter16 mm
Lap or starter length per bar0.8 m
Tie diameter8 mm
Tie spacing150 mm
Hooks per tie200 mm
Cover40 mm
Concrete wastage5 %
Results
Concrete to order2.42 m³
Concrete in cubic feet85.4 cft
16 mm main bars202 kg
8 mm ties88 ties
Tie steel58.3 kg
Total steel260.4 kg

How it is calculated

Concrete: width × depth × height, or π × (diameter ÷ 2)² × height, times the number of columns

Main bars: bars × (height + lap length) × columns

Ties: floor(height ÷ spacing) + 1 per column

Tie length: perimeter inside the cover + hooks

Steel weight: metres × d² ÷ 162.2

The lap or starter length and hook allowance are examples. Use the figures from your structural drawings and bar bending schedule, which also show any closer tie spacing near the joints.

Columns in the UAE

In villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman columns are normally cast with ready-mix concrete and reinforced with bars delivered in 12 m lengths, bought by the tonne. Use the result to check quantities and orders; the design itself follows the approved structural drawings.

Questions

Does the column height include the slab?

Measure it the way your quantities are taken. If the slab is measured through the column, use the height from the top of the slab below to the soffit of the slab above.

Why do the ties use the size inside the cover?

Ties wrap around the main bars, which sit inside the concrete cover, so their length follows the core of the column.