For contractors and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Choose the element, enter its size, and get the contact area of formwork in m² and ft², plus the number of 1.22 × 2.44 m plywood sheets for one use.
Worked example
With the calculator’s starting values:
| Element | Rectangular column |
|---|---|
| Width | 300 mm |
| Depth or thickness | 600 mm |
| Column height | 3 m |
| Number of identical elements | 1 |
| Cutting wastage on plywood | 10 % |
| Formwork area | 5.4 m² |
|---|---|
| In square feet | 58 ft² |
| Plywood sheets 1.22 × 2.44 m (one use) | 2 sheets |
How it is calculated
Slab: length × width + edge perimeter × thickness (enter the slab width in mm, for example 4000)
Beam: length × [2 × (depth − slab thickness) + width]
Rectangular column: 2 × (width + depth) × height
Round column: π × diameter × height (enter the diameter as the depth)
Wall: 2 × length × height + 2 × thickness × height (enter the height as the depth and the thickness as the width)
Footing: 2 × (length + width) × depth
The area is the face of concrete in contact with the formwork, which is how shuttering is normally measured. One plywood sheet of 1.22 × 2.44 m covers 2.977 m².
What it leaves out
Props, bearers, ties and the number of reuses are not included. Sheets are for a single use; divide by the number of reuses your shuttering team gets from a sheet to estimate purchase.
Shuttering in the UAE
On sites in Dubai, Sharjah, Abu Dhabi and Ajman formwork is often priced and measured per m², while plywood is bought by the sheet, so the result gives both. Column and wall areas are also quoted in ft² by some subcontractors.
Questions
Do I deduct the slab thickness from beam sides?
Yes, when the beam is cast with the slab, because the slab soffit formwork already covers the top part of each side. Set it to 0 for a beam cast on its own.
Why is the slab width entered in millimetres?
All widths in this calculator use millimetres so one field works for every element. A 4 m wide slab is 4000 mm.