Footing Concrete Calculator UAE: Pad Footings and Blinding

For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the footing size and number, and get the footing concrete, the blinding concrete under it, and the totals in m³ and cft.

Footing concrete to order16.33 m³

Worked example

With the calculator’s starting values:

Inputs
Length1.8 m
Width1.8 m
Depth600 mm
Number of footings8
Blinding thickness50 mm
Blinding projection each side100 mm
Wastage allowance5 %
Results
Footing concrete to order16.33 m³
Blinding concrete to order1.68 m³
Footing concrete in cft576.7 cft

How it is calculated

Footing = length × width × depth × number

Blinding = (length + 2 × projection) × (width + 2 × projection) × thickness × number

To order = net volume × (1 + wastage)

Blinding (also called PCC or lean concrete) is a thin layer under the footing that gives a clean, level base. Footing and blinding are usually different mixes, so they are shown separately.

Footings in the UAE

Villas and low-rise buildings in Dubai, Sharjah, Abu Dhabi and Ajman often sit on isolated or combined pad footings, sized by the structural engineer from the soil investigation. Below-ground concrete often needs protection such as waterproofing or a coating, and a sulphate-resisting mix where the specification calls for one, so check your drawings and specification.

Questions

Does this work for stepped footings?

Work out each step as its own rectangle, then add the results.

Where do I find the blinding thickness?

On the foundation details. 50 mm is only an example.