For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the column size, height and reinforcement, and get the concrete in m³ and cft, the main bars and ties, and the total steel weight.
Worked example
With the calculator’s starting values:
| Shape | Rectangular |
|---|---|
| Width | 300 mm |
| Depth | 600 mm |
| Height | 3.2 m |
| Number of columns | 4 |
| Number of bars | 8 |
| Bar diameter | 16 mm |
| Lap or starter length per bar | 0.8 m |
| Tie diameter | 8 mm |
| Tie spacing | 150 mm |
| Hooks per tie | 200 mm |
| Cover | 40 mm |
| Concrete wastage | 5 % |
| Concrete to order | 2.42 m³ |
|---|---|
| Concrete in cubic feet | 85.4 cft |
| 16 mm main bars | 202 kg |
| 8 mm ties | 88 ties |
| Tie steel | 58.3 kg |
| Total steel | 260.4 kg |
How it is calculated
Concrete: width × depth × height, or π × (diameter ÷ 2)² × height, times the number of columns
Main bars: bars × (height + lap length) × columns
Ties: floor(height ÷ spacing) + 1 per column
Tie length: perimeter inside the cover + hooks
Steel weight: metres × d² ÷ 162.2
The lap or starter length and hook allowance are examples. Use the figures from your structural drawings and bar bending schedule, which also show any closer tie spacing near the joints.
Columns in the UAE
In villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman columns are normally cast with ready-mix concrete and reinforced with bars delivered in 12 m lengths, bought by the tonne. Use the result to check quantities and orders; the design itself follows the approved structural drawings.
Questions
Does the column height include the slab?
Measure it the way your quantities are taken. If the slab is measured through the column, use the height from the top of the slab below to the soffit of the slab above.
Why do the ties use the size inside the cover?
Ties wrap around the main bars, which sit inside the concrete cover, so their length follows the core of the column.