For contractors, QS and site engineers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the pile diameter, length and number, and get the theoretical concrete, the quantity to order with overconsumption, and the volume per pile.
Worked example
With the calculator’s starting values:
| Diameter | 600 mm |
|---|---|
| Length to be concreted | 18 m |
| Number of piles | 24 |
| Overconsumption allowance | 10 % |
| Concrete to order | 134.36 m³ |
|---|---|
| Theoretical volume | 122.15 m³ |
| Per pile (with allowance) | 5.598 m³ |
| In cubic feet | 4,745 cft |
How it is calculated
Cross-section = π × (diameter ÷ 2)²
Per pile = cross-section × length
To order = per pile × number × (1 + overconsumption)
A 600 mm pile has a cross-section of 0.283 m², so each metre takes 0.283 m³ in theory. Actual consumption depends on the ground, the boring method and how the pile is cast, so compare the result with the pour records on site.
Piling in the UAE
Bored cast-in-place piles are widely used for buildings in Dubai, Sharjah, Abu Dhabi and Ajman, especially where the soil investigation shows loose sand or shallow groundwater near the coast. Pile sizes, lengths, concrete grade and cement type come from the piling design and specification; this calculator is for estimating and checking concrete orders.
Questions
Can I use this for round columns?
Yes. Enter the column diameter and height and set the overconsumption allowance to your usual wastage figure.
Does it include the pile cap?
No. Pile caps are rectangular, so use the concrete volume calculator or the footing calculator.