Retention Calculator UAE: Retention Money, Limit and Release

For contractors, subcontractors and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the contract value and the work done to date in AED with the retention rate and limit from your contract, and get the retention held, the payment after retention and the amounts released at completion and after the defects period.

Retention held to date40,000 AED

Worked example

With the calculator’s starting values:

Inputs
Contract value1,000,000 AED
Work done to date (gross)400,000 AED
Retention rate10 %
Retention limitCapped
Limit as % of contract value5 %
Released at completion50 %
Results
Retention held to date40,000 AED
Work done less retention360,000 AED
Total retention at completion50,000 AED
First release at completion25,000 AED
Second release after defects period25,000 AED

How it is calculated

Retention to date = work done × retention rate

Retention limit = contract value × limit %

Retention held = the smaller of the two

Retention at completion = the smaller of contract value × rate and the limit

First release = retention at completion × release %

Second release = retention at completion − first release

Once the retention held reaches the limit, later payments are made without any further retention. The amounts released assume the full contract value is certified; if the final account differs, enter the final value.

Defaults you can change

The 10% rate, 5% limit and 50% release at completion are example values, and the contract value and work done are placeholders. Use the rate, limit and release terms written in your contract.

Retention in the UAE

On projects in Dubai, Sharjah, Abu Dhabi and Ajman, retention is set in the main contract and is often passed down to subcontracts, and it is deducted from interim payments in AED. Check the rate, limit and release stages in your contract and payment certificates rather than assuming them, and keep a running total of retention held.

Questions

What happens when the retention limit is reached?

No more retention is deducted from later payments. The amount held stays at the limit until it is released.

Can retention be replaced by a bank guarantee?

Some contracts allow the contractor to replace retention with a retention bond or bank guarantee. Check your contract.

Should I enter amounts with or without VAT?

Use the same basis as your payment certificate. The calculator only applies the percentages to the amounts you enter.