For estimators, QS and contractors in Dubai, Sharjah, Abu Dhabi and Ajman. Enter your material cost, wastage, labour output and day rate, plant, overheads and profit in AED, and get the unit rate per m², m³, m, kg or number for your bill of quantities, plus the amount for the quantity.
Worked example
With the calculator’s starting values:
| Unit of measure | m² |
|---|---|
| Quantity | 100 |
| Material cost per unit | 40 AED |
| Material wastage | 5 % |
| Labour output | 10 units per man-day |
| Labour cost per man-day | 150 AED |
| Plant and equipment per unit | 5 AED |
| Overheads | 10 % |
| Profit | 10 % |
| VAT | No VAT |
| Unit rate | 75.02 AED/m² |
|---|---|
| Amount for the quantity | 7,502 AED |
How it is calculated
Material = material cost × (1 + wastage)
Labour = labour cost per man-day ÷ output per man-day
Direct cost = material + labour + plant
Overheads = direct cost × overheads %
Profit = (direct cost + overheads) × profit %
Unit rate = direct cost + overheads + profit
Amount = unit rate × quantity
With the starting values, labour is 150 ÷ 10 = 15 AED per m², the direct cost is 42 + 15 + 5 = 62 AED, overheads add 6.20 AED and profit adds 6.82 AED.
Some estimators apply profit on the direct cost only. If you do, the rate comes out slightly lower, so use the method your company prices with.
Defaults you can change
All the money figures, the 10 units per man-day output and the 5% wastage and 10% add-ons are placeholders to show the build-up, not market rates. Replace them with your own quotes, outputs and percentages.
Unit rates in the UAE
Bills of quantities in Dubai, Sharjah, Abu Dhabi and Ajman are priced in AED per m², m³, m, kg or number, and tender rates are usually entered before 5% VAT. Base material costs on current supplier quotes and labour outputs on your own records, and allow for the summer midday break for outdoor work when you set outputs.
Questions
Is profit added on top of overheads?
In this calculator, yes. Profit is applied to the direct cost plus overheads.
Where do labour outputs come from?
Your own site records are best. Outputs vary with the crew, the access and the weather, so check them against past jobs.
Should BOQ rates include VAT?
Rates are usually priced before VAT, with 5% VAT added to the total. Follow the tender instructions.