For contractors, site managers and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the crew size, working days, day or hourly rate in AED and any overtime, and get the labour cost, man-days, man-hours and the cost per m², m³, m or number of work done.
Worked example
With the calculator’s starting values:
| Number of workers | 4 |
|---|---|
| Working days | 5 days |
| Normal hours per day | 8 h |
| Rate basis | Per day |
| Normal rate per worker | 150 AED |
| Overtime hours per worker per day | 1 h |
| Overtime rate multiplier | 1.25 |
| On-costs | 0 % |
| Quantity of work done | 100 |
| Unit | m² |
| Labour cost | 3,468.75 AED |
|---|---|
| Labour cost per m² | 34.69 AED/m² |
| Man-days | 20 man-days |
| Man-hours including overtime | 180 man-hours |
How it is calculated
Man-days = workers × working days
Hourly rate = day rate ÷ normal hours (or the hourly rate you enter)
Normal time cost = man-days × day rate
Overtime cost = man-days × overtime hours × hourly rate × multiplier
Labour cost = (normal time + overtime) × (1 + on-costs)
Cost per unit = labour cost ÷ quantity of work done
With the starting values, the hourly rate is 150 ÷ 8 = 18.75 AED, normal time is 20 man-days × 150 = 3,000 AED and overtime is 20 × 1 × 18.75 × 1.25 = 468.75 AED.
Defaults you can change
The 150 AED day rate, the crew size, the hours and the 1.25 overtime multiplier are example values. Use your own rates, your labour supply contract and current labour law.
Labour costs in the UAE
Site labour in Dubai, Sharjah, Abu Dhabi and Ajman is priced per man-day or per hour in AED, either as direct staff or through labour supply companies. Outdoor work stops for the summer midday break, so plan the daily hours and outputs with that in mind, and check whether accommodation and transport are already in the rate before you add on-costs.
Questions
What overtime rate should I use in the UAE?
UAE labour law sets overtime pay at the normal wage plus at least 25%, and at least 50% for overtime between 10 pm and 4 am, except for shift workers. Check the current law and your employment or supply contracts.
Should the day rate include accommodation and transport?
It depends on how you pay the crew. If the rate does not include them, add them as on-costs.
How do I get a cost per m²?
Enter the quantity of work the crew completes in the same period. The calculator divides the labour cost by that quantity.