For electrical contractors, MEP engineers and site teams in the UAE: enter the load in kW, the supply (230 V single phase or 400 V three phase) and the correction factors, and get the design current, the breaker size and the minimum tabulated cable rating to look up in your cable table.
Worked example
With the calculator’s starting values:
| Supply | Three phase |
|---|---|
| Voltage (line to line) | 400 V |
| Load | 15 kW |
| Power factor | 0.9 |
| Breaker rating In | 0 A |
| Ambient temperature factor Ca | 0.91 |
| Grouping factor Cg | 1 |
| Thermal insulation factor Ci | 1 |
| Tabulated rating of the cable you picked | 0 A |
| Minimum tabulated rating It | 27.5 A |
|---|---|
| Design current Ib | 24.1 A |
| Breaker rating In | 25 A |
| Breaker check | Breaker at or above design current |
| Cable check | Enter a cable rating to check |
How it is calculated
Single phase: Ib = P × 1000 ÷ (V × pf)
Three phase: Ib = P × 1000 ÷ (√3 × V × pf)
In = next standard breaker size at or above Ib (6, 10, 16, 20, 25, 32, 40, 50, 63, 80, 100, 125 A and up), or your own
Minimum tabulated rating It = In ÷ (Ca × Cg × Ci)
Choose a cable whose tabulated rating for your installation method is at least It
Using the result
Look up the cable in the current-carrying capacity table for your cable type and installation method, for example multicore armoured XLPE cable clipped direct, on a tray or buried, and take the smallest size whose rating is at least the minimum It. Then check the voltage drop over the run length, because long runs often need a bigger cable than the current alone suggests.
Defaults you can change
The 0.91 ambient factor is an example for 90°C XLPE insulated cable in 40°C air. Buried cables, grouped cables and other insulation types use different factors, so replace all three factors with the ones from your wiring regulations or the cable maker’s data. The 0.9 power factor is a starting value; use the figure from the equipment data.
Cable sizing in the UAE
Low-voltage supplies in Dubai, Sharjah, Abu Dhabi and Ajman are 230 V single phase and 400 V three phase at 50 Hz. Summer air and ground temperatures are high, so the ambient correction factor matters and should not be skipped. The local utility’s wiring regulations apply, and the final cable size should be checked and signed off by a qualified electrical engineer.
Questions
Why does the calculator not give a size in mm²?
Ratings depend on the cable type, number of cores, installation method and the table you use, so the calculator gives the rating you need and you read the size from the table for your cable.
Does the breaker have to be at least the design current?
Yes. The breaker rating In should be at least the design current Ib, and the cable’s corrected rating should be at least In.
What power factor should I use?
Use the figure from the equipment data. Motors and some lighting run below 0.9.