For villa owners, contractors and QS in the UAE pricing electrical works: count the lighting, socket and AC points, add boards and cabling at your own rates in AED, and get a total with 5% VAT.
Worked example
With the calculator’s starting values:
| Lighting points | 30 nr |
|---|---|
| Socket points | 20 nr |
| AC and isolator points | 5 nr |
| Other points (data, TV, bell) | 5 nr |
| Rate per lighting point | 100 AED |
| Rate per socket point | 100 AED |
| Rate per AC point | 100 AED |
| Rate per other point | 100 AED |
| Distribution boards | 1 nr |
| Rate per distribution board | 1,000 AED |
| Main cables and containment (lump sum) | 0 AED |
| Testing, approvals and other (lump sum) | 0 AED |
| Contingency | 5 % |
| VAT | 5 % |
| Total with VAT | 7,717.5 AED |
|---|---|
| Total before VAT | 7,350 AED |
| VAT | 367.5 AED |
| Number of points | 60 points |
| All-in cost per point | 128.63 AED |
How it is calculated
Points cost = Σ (number of points × rate per point)
Subtotal = points cost + boards × rate per board + lump sums
Total before VAT = subtotal × (1 + contingency)
Total with VAT = total before VAT × (1 + VAT)
The 100 AED per point and 1,000 AED per board in the example are round placeholders that show the arithmetic. They are not market rates. Replace them with the rates in your contractor’s quote or your own price build-up.
What a point rate usually covers
A point rate normally covers the wiring from the board to the outlet, the back box, conduit and the switch or socket plate, but contractors draw the line in different places. Check whether light fittings, AC isolators, earthing, sub-main cables and testing are inside the point rate or priced separately, and put anything separate in the lump sums so it is not missed or counted twice.
Defaults you can change
The point counts, rates and the 5% contingency are examples. VAT is set to the UAE rate of 5%.
Electrical works in the UAE
Small electrical jobs in villas, flats and shops in Dubai, Sharjah, Abu Dhabi and Ajman are often quoted per point plus boards and cabling, which is how this calculator is laid out. New connections and load changes go through the emirate’s electricity authority, for example DEWA in Dubai and SEWA in Sharjah, so ask whether approvals, testing and inspection are in the price.
Questions
How do I count points?
Count each light outlet, switch-controlled fitting, socket, AC isolator and data or TV outlet shown on the drawings. A double socket is usually one point; check how your contractor counts them.
Should VAT be added to electrical works in the UAE?
Construction and maintenance services are generally charged at the standard 5% VAT rate when the contractor is VAT registered. Ask for quotes that show VAT separately.