For villa owners, contractors and QS in the UAE pricing electrical works: count the lighting, socket and AC points, add boards and cabling at your own rates in AED, and get a total with 5% VAT.

Total with VAT7,717.5 AED

Worked example

With the calculator’s starting values:

Inputs
Lighting points30 nr
Socket points20 nr
AC and isolator points5 nr
Other points (data, TV, bell)5 nr
Rate per lighting point100 AED
Rate per socket point100 AED
Rate per AC point100 AED
Rate per other point100 AED
Distribution boards1 nr
Rate per distribution board1,000 AED
Main cables and containment (lump sum)0 AED
Testing, approvals and other (lump sum)0 AED
Contingency5 %
VAT5 %
Results
Total with VAT7,717.5 AED
Total before VAT7,350 AED
VAT367.5 AED
Number of points60 points
All-in cost per point128.63 AED

How it is calculated

Points cost = Σ (number of points × rate per point)

Subtotal = points cost + boards × rate per board + lump sums

Total before VAT = subtotal × (1 + contingency)

Total with VAT = total before VAT × (1 + VAT)

The 100 AED per point and 1,000 AED per board in the example are round placeholders that show the arithmetic. They are not market rates. Replace them with the rates in your contractor’s quote or your own price build-up.

What a point rate usually covers

A point rate normally covers the wiring from the board to the outlet, the back box, conduit and the switch or socket plate, but contractors draw the line in different places. Check whether light fittings, AC isolators, earthing, sub-main cables and testing are inside the point rate or priced separately, and put anything separate in the lump sums so it is not missed or counted twice.

Defaults you can change

The point counts, rates and the 5% contingency are examples. VAT is set to the UAE rate of 5%.

Electrical works in the UAE

Small electrical jobs in villas, flats and shops in Dubai, Sharjah, Abu Dhabi and Ajman are often quoted per point plus boards and cabling, which is how this calculator is laid out. New connections and load changes go through the emirate’s electricity authority, for example DEWA in Dubai and SEWA in Sharjah, so ask whether approvals, testing and inspection are in the price.

Questions

How do I count points?

Count each light outlet, switch-controlled fitting, socket, AC isolator and data or TV outlet shown on the drawings. A double socket is usually one point; check how your contractor counts them.

Should VAT be added to electrical works in the UAE?

Construction and maintenance services are generally charged at the standard 5% VAT rate when the contractor is VAT registered. Ask for quotes that show VAT separately.