Inverted Roof Build-Up Calculator UAE

For waterproofing contractors, QS and villa owners in the UAE: enter the roof area in m² and the upstands, choose the top layer, and get the primer, membrane rolls, insulation boards, geotextile and screed, tiles or pebbles for an inverted roof.

Membrane rolls13 rolls

Worked example

With the calculator’s starting values:

Inputs
Roof area100 m²
Upstand perimeter40 m
Upstand height0.3 m
Membrane layers1 layer
Usable area per roll10 m²
Laps and wastage10 %
Primer coverage0.3 L/m²
Board length1200 mm
Board width600 mm
Board wastage5 %
Area per geotextile roll100 m²
Geotextile overlap10 %
Top layerScreed and tiles
Protection screed thickness50 mm
Tile wastage5 %
Results
Membrane rolls13 rolls
Primer33.6 litres
Insulation boards146 boards
Geotextile2 rolls
Protection screed5 m³
Roof tiles105 m²

How it is calculated

Waterproofed area = roof area + upstand perimeter × upstand height

Primer = waterproofed area × coverage

Membrane rolls = waterproofed area × layers × (1 + laps) ÷ roll area, rounded up

Insulation boards = roof area × (1 + wastage) ÷ board area, rounded up

Geotextile rolls = roof area × (1 + overlap) ÷ roll area, rounded up

Screed = roof area × thickness; tiles = roof area × (1 + wastage)

Pebbles = roof area × depth; weight = volume × bulk density

The layers of an inverted roof

From the slab up: screed to falls, primer, the waterproofing membrane turned up the upstands, insulation boards laid loose on the membrane, a geotextile separation layer, then a protection screed with tiles, or pebble ballast. Because the insulation sits above the membrane, the membrane is shielded from sun and temperature swings, and the insulation must be a type made to sit in wet conditions, such as extruded polystyrene (XPS).

Defaults you can change

Roll size, laps, primer coverage, board size, geotextile roll size, screed thickness, pebble depth and density are all example values. Replace them with the figures from the product data sheets and your roof detail. The insulation thickness should come from the U-value your project has to meet.

Roof waterproofing in the UAE

Flat concrete roofs on villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman are waterproofed and usually insulated, and the inverted build-up is a common way to keep the membrane out of the direct sun. Follow the system details from the membrane maker and your consultant, and flood test the membrane before the insulation goes down if your specification calls for it.

Questions

Why is there a geotextile in an inverted roof?

It separates the insulation from the screed or pebbles above, stops fines washing down between the boards, and lets water drain to the membrane below.

Does the membrane need to go up the parapet?

Yes. The membrane is turned up the upstands to the height on your detail, which is why upstand area is added to the waterproofed area.

Can I use pebbles instead of tiles?

Pebble ballast is used on roofs without regular foot traffic. Your designer should set the depth so the boards are held down against wind uplift and flotation.