Advance Payment Recovery Calculator UAE: Deduction per Certificate

For contractors, subcontractors and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the contract value in AED, the advance percentage and the certificate amounts, choose the recovery method in your contract, and get the advance recovered on this certificate and the balance still to recover.

Advance recovered this certificate37,500 AED

Worked example

With the calculator’s starting values:

Inputs
Contract value1,000,000 AED
Advance payment10 %
Recovery methodThreshold and rate
Start when certified work exceeds10 %
Recovery rate per certificate25 %
Certified before this certificate300,000 AED
This certificate amount (gross)150,000 AED
Advance already recovered50,000 AED
Results
Advance recovered this certificate37,500 AED
Certificate after recovery112,500 AED
Advance still to recover12,500 AED

How it is calculated

Advance = contract value × advance %

Threshold and rate: once certified work including this certificate exceeds start % × contract value, deduction = this certificate × recovery rate

Pro rata: deduction = this certificate × advance %

The deduction is never more than the advance still to recover

Balance = advance − recovered to date − this deduction

Two common recovery methods

With the threshold and rate method, recovery starts in the certificate in which the total certified work passes a stated share of the contract value, and a fixed share of each certificate is then deducted until the advance is repaid. FIDIC 1999 conditions use this pattern. With the pro rata method, each certificate repays the advance in the same proportion as the advance bears to the contract value, so the advance is cleared as the work is completed.

The calculator works on gross certificate amounts before retention and other deductions. Your contract may define the amounts differently.

Defaults you can change

The 10% advance, 10% start point and 25% recovery rate are example values, and the contract and certificate amounts are placeholders. Use the figures in your contract and payment certificates.

Advance payments in the UAE

On projects in Dubai, Sharjah, Abu Dhabi and Ajman, an advance is usually paid against an advance payment guarantee from a bank, and the guarantee may reduce as the advance is recovered. Keep a running record in AED of the amount recovered on each certificate, and check the start point and rate against your contract.

Questions

When does advance recovery start?

When your contract says. With the threshold method it starts in the certificate in which certified work passes the stated percentage; with the pro rata method it starts with the first certificate.

What if the advance is not fully recovered by completion?

Contracts usually make the unrecovered balance due at completion or on termination. Check your contract.

Is VAT charged on an advance payment in the UAE?

An advance payment can create a VAT point when it is received, so check the VAT treatment with your tax adviser.

Shopping Cart
Scroll to Top