For contractors, subcontractors and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the contract value and the work done to date in AED with the retention rate and limit from your contract, and get the retention held, the payment after retention and the amounts released at completion and after the defects period.
Worked example
With the calculator’s starting values:
| Contract value | 1,000,000 AED |
|---|---|
| Work done to date (gross) | 400,000 AED |
| Retention rate | 10 % |
| Retention limit | Capped |
| Limit as % of contract value | 5 % |
| Released at completion | 50 % |
| Retention held to date | 40,000 AED |
|---|---|
| Work done less retention | 360,000 AED |
| Total retention at completion | 50,000 AED |
| First release at completion | 25,000 AED |
| Second release after defects period | 25,000 AED |
How it is calculated
Retention to date = work done × retention rate
Retention limit = contract value × limit %
Retention held = the smaller of the two
Retention at completion = the smaller of contract value × rate and the limit
First release = retention at completion × release %
Second release = retention at completion − first release
Once the retention held reaches the limit, later payments are made without any further retention. The amounts released assume the full contract value is certified; if the final account differs, enter the final value.
Defaults you can change
The 10% rate, 5% limit and 50% release at completion are example values, and the contract value and work done are placeholders. Use the rate, limit and release terms written in your contract.
Retention in the UAE
On projects in Dubai, Sharjah, Abu Dhabi and Ajman, retention is set in the main contract and is often passed down to subcontracts, and it is deducted from interim payments in AED. Check the rate, limit and release stages in your contract and payment certificates rather than assuming them, and keep a running total of retention held.
Questions
What happens when the retention limit is reached?
No more retention is deducted from later payments. The amount held stays at the limit until it is released.
Can retention be replaced by a bank guarantee?
Some contracts allow the contractor to replace retention with a retention bond or bank guarantee. Check your contract.
Should I enter amounts with or without VAT?
Use the same basis as your payment certificate. The calculator only applies the percentages to the amounts you enter.