For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the area to blind and the thickness, and get the blinding concrete in m³ and cft, plus cement bags, sand and aggregate if you mix it on site.
Worked example
With the calculator’s starting values:
| Length | 12 m |
|---|---|
| Width | 8 m |
| Number of identical areas | 1 |
| Thickness | 50 mm |
| Mix ratio (cement : sand : aggregate) | 1 : 3 : 6 |
| Wastage allowance | 5 % |
| Blinding concrete | 5.04 m³ |
|---|---|
| In cubic feet | 178 cft |
| Cement | 23 bags of 50 kg |
| Sand | 2.33 m³ |
| Aggregate | 4.66 m³ |
How it is calculated
Volume = length × width × thickness × number × (1 + wastage)
Dry volume = wet volume × 1.54
Each material = dry volume × its share of the ratio
Cement bags = cement volume × 1,440 kg/m³ ÷ 50 kg
The 1.54 dry-volume factor and 1,440 kg/m³ cement density are the usual rule-of-thumb figures for nominal mixes. For ready-mix blinding, order the volume and ignore the material lines.
Blinding in the UAE
On projects in Dubai, Sharjah, Abu Dhabi and Ajman blinding (often called PCC or lean concrete) is laid under footings, tie beams and ground slabs, and is either ordered as ready-mix or mixed on site for small areas with cement in 50 kg bags. The thickness and grade come from the foundation details and specification.
Questions
What is the difference between blinding and PCC?
On most sites they mean the same thing: a thin layer of plain (unreinforced) concrete that gives a clean, level base for the work above.
Should the blinding be bigger than the footing?
Usually it projects a little beyond the footing on each side. Add the projection to the length and width, or use the footing calculator, which includes it.