Enter the wall size, openings and brick size, and get the number of bricks plus the mortar, 50 kg cement bags and sand to lay them. For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman working in m², m³ and 50 kg bags.
Worked example
With the calculator’s starting values:
| Wall length | 10 m |
|---|---|
| Wall height | 3 m |
| Openings to deduct | 2 m² |
| Brick length | 215 mm |
| Brick height | 65 mm |
| Brick width | 102.5 mm |
| Wall thickness | Half brick (one leaf) |
| Mortar joint | 10 mm |
| Mortar mix (cement : sand) | 1 : 4 |
| Brick wastage | 5 % |
| Bricks needed | 1,743 bricks |
|---|---|
| Cement for mortar | 4 bags of 50 kg |
| Sand for mortar | 0.52 m³ |
How it is calculated
Bricks per m² = leaves ÷ [(brick length + joint) × (brick height + joint)]
Bricks = (wall area − openings) × bricks per m² × (1 + wastage)
Mortar = wall volume − volume taken by the bricks
Cement and sand = mortar × 1.33 dry factor, split by the mix ratio
With a 215 × 65 mm brick face and 10 mm joints, each brick covers 0.225 × 0.075 m, which gives about 59 bricks per m² for each leaf. A one-brick wall has two leaves plus the collar joint between them.
Defaults you can change
The brick size, joint, mix and 5% wastage are example values. Measure the bricks you are buying, as sizes vary between makers. Cement uses 1,440 kg/m³ and 50 kg bags, and the mortar figure assumes all joints are filled.
Brickwork in the UAE
Concrete blocks are the main walling unit in Dubai, Sharjah, Abu Dhabi and Ajman, so bricks are mostly used for feature walls, garden walls, planters and small repair work. Bricks are sold per piece or per pallet and sizes differ between clay facing bricks and cement bricks, so enter the actual size before you compare quotes. Check the brick type and mortar mix against the drawings or the consultant’s specification.
Questions
How many bricks are in 1 m² of wall?
About 59 for a half-brick wall of 215 × 102.5 × 65 mm bricks with 10 mm joints, and about 119 for a one-brick wall.
How much mortar does brickwork need?
With the starting values, about 0.018 m³ of wet mortar per m² of half-brick wall. Thicker joints or a one-brick wall need more.
What wastage should I allow for bricks?
5% is an example. Breakage and cutting vary with the brick and the job, so use your own figure.