For waterproofing contractors, QS and villa owners in the UAE: enter the roof area in m² and the upstands, choose the top layer, and get the primer, membrane rolls, insulation boards, geotextile and screed, tiles or pebbles for an inverted roof.
Worked example
With the calculator’s starting values:
| Roof area | 100 m² |
|---|---|
| Upstand perimeter | 40 m |
| Upstand height | 0.3 m |
| Membrane layers | 1 layer |
| Usable area per roll | 10 m² |
| Laps and wastage | 10 % |
| Primer coverage | 0.3 L/m² |
| Board length | 1200 mm |
| Board width | 600 mm |
| Board wastage | 5 % |
| Area per geotextile roll | 100 m² |
| Geotextile overlap | 10 % |
| Top layer | Screed and tiles |
| Protection screed thickness | 50 mm |
| Tile wastage | 5 % |
| Membrane rolls | 13 rolls |
|---|---|
| Primer | 33.6 litres |
| Insulation boards | 146 boards |
| Geotextile | 2 rolls |
| Protection screed | 5 m³ |
| Roof tiles | 105 m² |
How it is calculated
Waterproofed area = roof area + upstand perimeter × upstand height
Primer = waterproofed area × coverage
Membrane rolls = waterproofed area × layers × (1 + laps) ÷ roll area, rounded up
Insulation boards = roof area × (1 + wastage) ÷ board area, rounded up
Geotextile rolls = roof area × (1 + overlap) ÷ roll area, rounded up
Screed = roof area × thickness; tiles = roof area × (1 + wastage)
Pebbles = roof area × depth; weight = volume × bulk density
The layers of an inverted roof
From the slab up: screed to falls, primer, the waterproofing membrane turned up the upstands, insulation boards laid loose on the membrane, a geotextile separation layer, then a protection screed with tiles, or pebble ballast. Because the insulation sits above the membrane, the membrane is shielded from sun and temperature swings, and the insulation must be a type made to sit in wet conditions, such as extruded polystyrene (XPS).
Defaults you can change
Roll size, laps, primer coverage, board size, geotextile roll size, screed thickness, pebble depth and density are all example values. Replace them with the figures from the product data sheets and your roof detail. The insulation thickness should come from the U-value your project has to meet.
Roof waterproofing in the UAE
Flat concrete roofs on villas and buildings in Dubai, Sharjah, Abu Dhabi and Ajman are waterproofed and usually insulated, and the inverted build-up is a common way to keep the membrane out of the direct sun. Follow the system details from the membrane maker and your consultant, and flood test the membrane before the insulation goes down if your specification calls for it.
Questions
Why is there a geotextile in an inverted roof?
It separates the insulation from the screed or pebbles above, stops fines washing down between the boards, and lets water drain to the membrane below.
Does the membrane need to go up the parapet?
Yes. The membrane is turned up the upstands to the height on your detail, which is why upstand area is added to the waterproofed area.
Can I use pebbles instead of tiles?
Pebble ballast is used on roofs without regular foot traffic. Your designer should set the depth so the boards are held down against wind uplift and flotation.