Enter the net blockwork area, block size and mix, and get the wet mortar, 50 kg cement bags and sand to lay the blocks. For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman working with 400 × 200 blocks, m² and m³.
Worked example
With the calculator’s starting values:
| Net wall area | 28 m² |
|---|---|
| Block face (length × height) | 400 × 200 mm |
| Block thickness | 200 mm |
| Mortar joint | 10 mm |
| Mortar mix (cement : sand) | 1 : 4 |
| Dry volume factor | 1.33 |
| Cement bulk density | 1440 kg/m³ |
| Cement bag weight | 50 kg |
| Mortar wastage | 10 % |
| Cement bags | 4 bags of 50 kg |
|---|---|
| Wet mortar with wastage | 0.436 m³ |
| Cement weight | 167 kg |
| Sand | 0.46 m³ |
How it is calculated
Blocks = wall area ÷ [(block length + joint) × (block height + joint)]
Mortar = wall area × thickness − blocks × block volume
Wet mortar with wastage = mortar × (1 + wastage)
Dry volume = wet mortar × dry volume factor
Cement = dry volume ÷ (1 + sand parts) × bulk density; sand = dry volume × sand parts ÷ (1 + sand parts)
The mortar figure assumes a full bed with every joint filled, as for solid blocks. Hollow blocks laid on their face shells use less, so treat the result as an upper limit for hollow work.
Defaults you can change
The 1.33 dry factor, 1,440 kg/m³ cement density, 10% mortar wastage and the 1 : 4 mix are typical values. Replace them with your specification or your own site figures.
Blockwork mortar in the UAE
Site-mixed cement and sand mortar is common for hollow and solid block walls in Dubai, Sharjah, Abu Dhabi and Ajman, with cement in 50 kg bags and washed sand bought by the m³ or by the truck. Bagged premixed masonry mortars are also available. In summer, mix small batches so the mortar is used before it stiffens, and follow the mix in the consultant’s specification.
Questions
How much mortar is needed per m² of 200 mm blockwork?
With 400 × 200 × 200 mm blocks and 10 mm joints, about 0.014 m³ per m² of wall before wastage, assuming a full bed.
What mortar mix is used for blockwork?
1 : 4 to 1 : 6 cement to sand is common, but the mix on your project should come from the specification.
Why is the answer in 50 kg bags?
Cement for site mixing is normally sold in 50 kg bags in the UAE. Change the bag weight if yours differ.