Pile Concrete Calculator UAE: Bored Piles and Round Columns

For contractors, QS and site engineers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the pile diameter, length and number, and get the theoretical concrete, the quantity to order with overconsumption, and the volume per pile.

Concrete to order134.36 m³

Worked example

With the calculator’s starting values:

Inputs
Diameter600 mm
Length to be concreted18 m
Number of piles24
Overconsumption allowance10 %
Results
Concrete to order134.36 m³
Theoretical volume122.15 m³
Per pile (with allowance)5.598 m³
In cubic feet4,745 cft

How it is calculated

Cross-section = π × (diameter ÷ 2)²

Per pile = cross-section × length

To order = per pile × number × (1 + overconsumption)

A 600 mm pile has a cross-section of 0.283 m², so each metre takes 0.283 m³ in theory. Actual consumption depends on the ground, the boring method and how the pile is cast, so compare the result with the pour records on site.

Piling in the UAE

Bored cast-in-place piles are widely used for buildings in Dubai, Sharjah, Abu Dhabi and Ajman, especially where the soil investigation shows loose sand or shallow groundwater near the coast. Pile sizes, lengths, concrete grade and cement type come from the piling design and specification; this calculator is for estimating and checking concrete orders.

Questions

Can I use this for round columns?

Yes. Enter the column diameter and height and set the overconsumption allowance to your usual wastage figure.

Does it include the pile cap?

No. Pile caps are rectangular, so use the concrete volume calculator or the footing calculator.