For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the slab size, bar size and spacing each way, and get the number of bars, the total length, the weight in kg and tonnes, and how many 12 m bars to order.
Worked example
With the calculator’s starting values:
| Slab length | 6 m |
|---|---|
| Slab width | 4 m |
| Concrete cover | 25 mm |
| Bar diameter | 12 mm |
| Spacing | 150 mm |
| Bar diameter | 10 mm |
| Spacing | 200 mm |
| Number of meshes | Bottom only |
| Laps, bends and wastage | 8 % |
| Total steel | 233 kg |
|---|---|
| Total steel | 0.233 tonnes |
| 12 mm bars | 173.5 m |
| 12 mm bars to order | 15 bars of 12 m |
| 10 mm bars | 128 m |
| 10 mm bars to order | 11 bars of 12 m |
How it is calculated
Clear length = slab length − 2 × cover (same for the width)
Bars along the length = floor(clear width ÷ spacing) + 1
Bars along the width = floor(clear length ÷ spacing) + 1
Metres = bars × bar length × meshes × (1 + allowance)
Weight (kg) = metres × d² ÷ 162.2, with d in mm
d² ÷ 162.2 is the weight per metre of steel at 7,850 kg/m³, so a 12 mm bar weighs 0.888 kg/m and a 10 mm bar 0.617 kg/m.
What it leaves out
This is a plain rectangular mesh. Add extra top bars over supports, trimmer bars at openings, chairs and edge U-bars separately, from your structural drawings. For a quick weight check of any bar list, use the rebar weight calculator.
Slab steel in the UAE
On projects in Dubai, Sharjah, Abu Dhabi and Ajman rebar is delivered in 12 m lengths and bought by weight, so the result gives both tonnes and the number of 12 m bars per size. The slab reinforcement itself must follow the approved structural drawings and bar bending schedule; this calculator is for estimating and checking quantities.
Questions
Why is one bar added to the count?
Bars are placed at both edges of the clear width, so a run divided into spaces always needs one more bar than the number of spaces.
What allowance should I use for laps?
It depends on bar size, lap length and how many 12 m lengths each run needs. 8% is only an example; take the figure from your bar bending schedule.
Is rebar sold by the bar or by the tonne in the UAE?
Suppliers usually price reinforcement per tonne, and deliver it as 12 m bars or cut and bent to the schedule. That is why the calculator shows both.