For contractors and site engineers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the concrete volume and the truck size your plant uses, and get the number of truckloads, the size of the last load, and an estimate of the pour time.
Worked example
With the calculator’s starting values:
| Concrete volume | 45 m³ |
|---|---|
| Wastage allowance | 3 % |
| Truck load | 9 m³ |
| Placing rate | 25 m³/hour |
| Time between trucks | 20 minutes |
| Truckloads | 6 trucks |
|---|---|
| Concrete to order | 46.35 m³ |
| Last truck carries | 1.35 m³ |
| Estimated pour time | 1.9 hours |
| Truck interval check | Trucks keep up with placing |
How it is calculated
Concrete to order = volume × (1 + wastage)
Truckloads = order ÷ truck load, rounded up
Last load = order − (truckloads − 1) × truck load
Pour time = order ÷ placing rate
Minutes to place one truck = truck load ÷ placing rate × 60
The interval check compares how often trucks arrive with how fast one load is placed. If trucks arrive less often than you place a load, the pump will stand waiting and you risk cold joints, so ask the plant for more trucks on the run.
Ready-mix pours in the UAE
Most structural concrete in Dubai, Sharjah, Abu Dhabi and Ajman is supplied by ready-mix plants in transit mixers, and the load per truck depends on the plant and the mix. In the hot months many large pours are planned for the cooler hours, so confirm the schedule, travel time and the plant’s minimum order before you book.
Questions
Should I order the exact volume?
No. A small shortfall stops the pour, so allow some wastage and confirm the final top-up quantity with the plant during the pour.
Why does the last truck carry less?
The order rarely divides into full loads. The last truck brings the balance; some plants charge a minimum for part loads.