Ready-Mix Truck Calculator UAE: Truckloads and Pour Time

For contractors and site engineers in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the concrete volume and the truck size your plant uses, and get the number of truckloads, the size of the last load, and an estimate of the pour time.

Truckloads6 trucks

Worked example

With the calculator’s starting values:

Inputs
Concrete volume45 m³
Wastage allowance3 %
Truck load9 m³
Placing rate25 m³/hour
Time between trucks20 minutes
Results
Truckloads6 trucks
Concrete to order46.35 m³
Last truck carries1.35 m³
Estimated pour time1.9 hours
Truck interval checkTrucks keep up with placing

How it is calculated

Concrete to order = volume × (1 + wastage)

Truckloads = order ÷ truck load, rounded up

Last load = order − (truckloads − 1) × truck load

Pour time = order ÷ placing rate

Minutes to place one truck = truck load ÷ placing rate × 60

The interval check compares how often trucks arrive with how fast one load is placed. If trucks arrive less often than you place a load, the pump will stand waiting and you risk cold joints, so ask the plant for more trucks on the run.

Ready-mix pours in the UAE

Most structural concrete in Dubai, Sharjah, Abu Dhabi and Ajman is supplied by ready-mix plants in transit mixers, and the load per truck depends on the plant and the mix. In the hot months many large pours are planned for the cooler hours, so confirm the schedule, travel time and the plant’s minimum order before you book.

Questions

Should I order the exact volume?

No. A small shortfall stops the pour, so allow some wastage and confirm the final top-up quantity with the plant during the pour.

Why does the last truck carry less?

The order rarely divides into full loads. The last truck brings the balance; some plants charge a minimum for part loads.