For Dubai consultants, MEP engineers and developers working to the Al Sa’fat green building system: enter the building electrical load or the common-area lighting load in kWh or kW, and get the minimum solar PV size in kWp, the number of panels and a quick check of your proposed system.
Worked example
With the calculator’s starting values:
| Requirement route | Share of building electrical load |
|---|---|
| Load entered as | Energy per year (kWh) |
| Building electrical load | 400,000 kWh/yr |
| Share required | 10 % |
| Peak sun hours per day | 5.5 h |
| Performance ratio | 0.8 |
| Panel rating | 550 W |
| Proposed PV size | 30 kWp |
| Minimum PV size | 24.91 kWp |
|---|---|
| Panels at this rating | 46 panels |
| Proposed PV size | 30 kWp |
| Check | Meets the requirement |
How it is calculated
Route 1: target = building electrical load × 10%
Route 2: target = common-area lighting load × 30%, and at least 20 kWp
For an energy target: kWp = target kWh ÷ (peak sun hours × 365 × performance ratio)
For a power target: kWp = target kW
Panels = kWp × 1,000 ÷ panel watts, rounded up
What the requirement says
Al Sa’fat, the Dubai Green Building System published by Dubai Municipality, includes an on-site renewable energy requirement for electrical power generation (section 504.03) at the Golden Sa’fa level. It asks for on-site solar generation of 10% of the building electrical load, leaving out fire fighting systems and air-conditioning units and pumps, or, where there is not enough space, a system covering 30% of the common-area lighting load with a minimum of 20 kWp. Figures checked November 2026 against the published Al Sa’fat text.
The code text does not spell out every detail of how the load is measured, so check with Dubai Municipality and your consultant whether your project should use annual energy or connected power. Every share and the minimum size are editable in case the code changes.
This is a quick check against the published code. Dubai Municipality as the approving authority and the project consultant have the final say.
Solar PV for green buildings in the UAE
Al Sa’fat applies to buildings in Dubai and sets Silver Sa’fa as the base level, with Golden and Platinum adding requirements such as this one. Grid-connected rooftop systems in Dubai are approved and connected through DEWA’s Shams Dubai programme. Projects in Sharjah, Abu Dhabi and Ajman follow their own authority’s green building rules and utility connection conditions, so do not apply this check outside Dubai.
Questions
Does this apply to every building in Dubai?
No. The electrical generation item is part of the Golden Sa’fa level, so it applies to projects that must or choose to reach Golden or Platinum. Check your project’s required level with Dubai Municipality.
Which loads can I leave out?
The requirement excludes fire fighting systems and air-conditioning units and pumps from the electrical load. Include the other building loads.
Where do the peak sun hours come from?
Use the yield from your PV design software or your installer. The default of 5.5 hours is an example only.