For site engineers and concrete contractors in the UAE: enter the air temperature, humidity, wind speed and concrete temperature on pour day, and see the evaporation rate in kg/m²/h against your limit before you place a slab.
Worked example
With the calculator’s starting values:
| Air temperature | 38 °C |
|---|---|
| Relative humidity | 40 % |
| Wind speed | 15 km/h |
| Concrete temperature | 35 °C |
| Evaporation limit | 1 kg/m²/h |
| Evaporation rate | 1.05 kg/m²/h |
|---|---|
| Verdict | Above your limit: take precautions |
| Your limit | 1 kg/m²/h |
| Water lost from each m² in one hour | 1.05 litres |
How it is calculated
E = 5 × [(Tc + 18)2.5 − r × (Ta + 18)2.5] × (V + 4) × 10−6
E = evaporation rate in kg/m²/h; Tc = concrete temperature °C; Ta = air temperature °C; r = relative humidity as a decimal; V = wind speed in km/h
This is the equation published by Paul Uno in 1998 as a formula version of the evaporation chart in ACI 305, the American Concrete Institute guide to hot weather concreting. One kg of water per m² is a 1 mm layer, so 1.05 kg/m²/h means the surface loses about 1 mm of water an hour.
What to do when the rate is high
Commonly recommended steps are windbreaks and sunshades, fog spraying above the surface, an evaporation retarder after screeding, cooler concrete, and curing as soon as finishing allows. Your specification may set its own measures.
Defaults you can change
The weather and concrete temperatures are example values for a hot day. Measure them at the pour. The 1.0 kg/m²/h limit is the figure commonly used as the point where precautions are needed; 0.5 kg/m²/h is often used for concrete with silica fume or a low water-cement ratio. Use the limit in your specification.
Hot-weather concreting in the UAE
Summer pours in Dubai, Sharjah, Abu Dhabi and Ajman combine high air and concrete temperatures, and on some days wind or low humidity, which can push the evaporation rate past 1 kg/m²/h. Many sites pour slabs early in the morning or at night, cool the concrete with chilled water or ice, and start curing straight after finishing. Check the hot-weather clauses in your project specification.
Questions
What evaporation rate causes plastic shrinkage cracks?
Cracking becomes likely when water leaves the surface faster than bleed water rises. 1.0 kg/m²/h is the figure commonly used to trigger precautions, and 0.5 kg/m²/h for mixes with little bleeding, such as silica fume concrete.
Which matters more, wind or temperature?
Both. Wind multiplies the whole result, and a concrete temperature above the air temperature raises it sharply, especially when the air is dry. Try changing one input at a time to see the effect.
Is a night pour better in the UAE?
Usually the air and concrete are cooler at night, which lowers the rate, but humidity and wind change too. Put the expected night readings into the calculator to check.