For contractors, site engineers and HR teams in the UAE: enter the shift times and the number of workers, and check if the shift falls inside the summer midday break and what the fine could be in AED.
Worked example
With the calculator’s starting values:
| Is the work date between 15 June and 15 September? | Yes |
|---|---|
| Is the work outdoors in direct sun? | Yes |
| Shift start | 07:00 |
| Shift end | 17:00 |
| Workers on this shift | 10 workers |
| Break starts | 12:30 |
| Break ends | 15:00 |
| Fine per worker | 5,000 AED |
| Maximum fine | 50,000 AED |
| Shift check | Overlaps the midday break |
|---|---|
| Shift hours inside the break window | 2.5 hours |
| Possible fine, up to | 50,000 AED |
How it is calculated
Overlap = time where the shift and the break window (12:30 to 15:00) meet
Overnight shifts are counted across midnight
Possible fine = workers × AED 5,000, capped at AED 50,000
No fine is shown outside 15 June to 15 September or for shaded or exempt work
The midday break is set each year by the Ministry of Human Resources and Emiratisation (MOHRE). For 2025 and 2026 it ran from 15 June to 15 September, 12:30 pm to 3:00 pm, with a fine of AED 5,000 per worker up to AED 50,000. Rules checked November 2026. MOHRE confirms the dates each year and exempts some work that must continue for technical reasons, with conditions, so check mohre.gov.ae before you plan. This is a quick check and not legal advice.
The midday break in the UAE
The midday break applies to outdoor work in direct sun across Dubai, Sharjah, Abu Dhabi and Ajman. Employers must also give shaded rest areas and drinking water during the break. Many sites start early in the morning and resume after 3 pm to keep the same daily hours.
Questions
When does the UAE midday break start?
It has run from 15 June to 15 September in recent years. MOHRE announces the dates each year.
Does the break count as working hours?
The break is a rest period. Plan the shift so daily hours stay within the legal limit, with work before and after the break.