For contractors, QS and clients in Dubai, Sharjah, Abu Dhabi and Ajman. Enter a base amount in AED and either the base and current index from your contract or a yearly escalation rate, and get the adjusted amount and the escalation.
Worked example
With the calculator’s starting values:
| Escalate by | Index change |
|---|---|
| Base amount | 100,000 AED |
| Fixed portion | 15 % |
| Base index | 100 |
| Current index | 108 |
| Adjusted amount | 106,800 AED |
|---|---|
| Escalation amount | 6,800 AED |
| Escalation | 6.8 % |
How it is calculated
Index method: factor = fixed portion + (1 − fixed portion) × current index ÷ base index
Yearly rate: factor = (1 + rate) ^ years
Adjusted amount = base amount × factor
Escalation = adjusted amount − base amount
The fixed portion is the part of the price the contract does not adjust, often to cover overheads and profit. With 15% fixed and an index that rises 8%, the price rises 0.85 × 8% = 6.8%.
Defaults you can change
The 100,000 AED base, the index values, the 15% fixed portion and the 3% yearly rate are placeholders to show the method, not published figures. Use the index, base date and fixed portion named in your contract.
Price escalation in the UAE
Steel, cement and other material prices can move during a long project in Dubai, Sharjah, Abu Dhabi or Ajman. Some contracts include a price adjustment clause and many fixed-price contracts do not, so check yours first, then use the index it names and keep supplier quotes in AED as backup for any claim.
Questions
What is the fixed portion?
The share of the price that is not adjusted when the index changes. Your contract states it, or it may be zero.
Does a fall in the index reduce the price?
With an index formula that works both ways, yes. The calculator then shows a negative escalation.
Can I use a yearly rate instead of an index?
Yes, for budgeting. The yearly rate method compounds the rate over the number of years you enter.