For contractors, QS and home owners in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the beam length, width and depth, and get the concrete in m³ and cft, the ready-mix order and the formwork area.
Worked example
With the calculator’s starting values:
| Clear length | 5 m |
|---|---|
| Width | 300 mm |
| Overall depth | 600 mm |
| Slab thickness to deduct | 150 mm |
| Number of identical beams | 6 |
| Wastage allowance | 5 % |
| Concrete to order | 4.25 m³ |
|---|---|
| In cubic feet | 150.2 cft |
| Ready-mix order (rounded up to 0.5 m³) | 4.5 m³ |
| Formwork area (sides and soffit) | 36 m² |
How it is calculated
Depth below slab = overall depth − slab thickness
Concrete = clear length × width × depth below slab × number of beams
To order = concrete × (1 + wastage)
Formwork = clear length × (2 × depth below slab + width) × number of beams
When a beam is cast with the slab, the part within the slab thickness is usually measured with the slab, so it is deducted here. Measure the clear length between the faces of the columns or walls the beam spans to.
Beams in the UAE
On projects in Dubai, Sharjah, Abu Dhabi and Ajman beams and slabs are usually poured together with ready-mix concrete, so add the slab volume from the concrete volume calculator to get the full pour. Suppliers and gangs may quote in cubic feet, which is why both units are shown.
Questions
Should I use the clear span or the centre-to-centre length?
Use the clear length between supports, because the concrete within the columns is normally measured with the columns.
Does this include the steel?
No. Use the rebar weight calculator with the bar list from your drawings.