Worked example

With the calculator’s starting values:

Inputs
Contract sum1,000,000 AED
Value of work done to date400,000 AED
Approved variations done to date20,000 AED
Materials on site allowed30,000 AED
Retention rate10 %
Retention limit5 % of contract
Advance payment recovered to date40,000 AED
Other deductions to date0 AED
Net amount certified before250,000 AED
VATAdd 5% VAT
Results
Amount due this certificate120,750 AED
Gross valuation to date450,000 AED
Less retention held45,000 AED
Less advance recovered40,000 AED
Net valuation to date365,000 AED
Less previous certificates250,000 AED
Due before VAT115,000 AED
VAT at 5%5,750 AED

How it is calculated

Gross valuation = work done + approved variations + materials on site (all to date)

Retention held = gross valuation × retention rate, but not more than contract sum × retention limit

Net valuation = gross valuation − retention − advance recovered − other deductions

Due before VAT = net valuation − net amount certified before

Amount due = due before VAT × (1 + VAT rate)

With the starting values, the gross valuation is 400,000 + 20,000 + 30,000 = 450,000 AED. Retention at 10% is 45,000 AED, below the 5% limit of 50,000 AED, so 45,000 AED is held. The net valuation is 450,000 − 45,000 − 40,000 = 365,000 AED, and after the 250,000 AED already certified, 115,000 AED is due before VAT.

Work in cumulative figures

Every figure except VAT is a total to date, not the amount for this month. Working cumulatively keeps retention and advance recovery right when earlier valuations are corrected. If the result is negative, more has been certified before than the work now supports.

Defaults you can change

The 10% retention rate, the 5% limit and all the amounts are example values. Use the rates, limits and payment terms in your own contract.

Interim payments in the UAE

Projects in Dubai, Sharjah, Abu Dhabi and Ajman are often let on FIDIC-based or bespoke contracts, with interim payments valued on work done to date. Retention, advance recovery and the treatment of materials on site come from the contract, so check each figure against the conditions of contract and the consultant’s valuation before you issue the invoice.

Questions

Is VAT charged on interim payments in the UAE?

VAT is normally charged at the standard 5% rate on the amount invoiced for construction work. Retention is usually dealt with when it is invoiced and released, so check the timing with your accountant.

Why is retention calculated on the gross valuation?

Retention is usually a percentage of the value of work done to date, held until completion and the end of the defects period. Some contracts treat materials on site differently, so follow your contract.

Where do I get the advance recovered to date?

From your recovery schedule or the previous certificates. The Advance Payment Recovery Calculator works it out from the contract terms.

Shopping Cart
Scroll to Top