Liquidated Damages Calculator UAE: Delay Damages and Cap

For contractors, clients and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the contract value in AED, the days late, any extension of time and the liquidated damages rate and cap from your contract, and get the delay damages and the days left until the cap is reached.

Liquidated damages20,000 AED

Worked example

With the calculator’s starting values:

Inputs
Contract value1,000,000 AED
Days late30 days
Extension of time granted10 days
Rate basisAED per day
LD rate per day1,000 AED
Cap on damagesCapped
Cap as % of contract value10 %
Results
Liquidated damages20,000 AED
Days of delay charged20 days
Damages per day1,000 AED
Cap amount100,000 AED
Days until the cap is reached100 days

How it is calculated

Days charged = days late − extension of time (not below 0)

Damages per day = AED rate, or contract value × % per day, or contract value × % per week ÷ 7

Liquidated damages = days charged × damages per day

With a cap: the smaller of that and contract value × cap %

Days until the cap = cap amount ÷ damages per day

The result is a calculation aid, not legal advice. Whether damages are due, and for how many days, depends on the contract, notices, extensions of time and any delay caused by the employer.

Defaults you can change

The 1,000 AED per day rate, the 0.1% option and the 10% cap are example values, and the contract value and days are placeholders. Use the rate, basis and cap stated in your contract.

Liquidated damages in the UAE

Construction contracts in Dubai, Sharjah, Abu Dhabi and Ajman usually state delay damages in AED per day or week, or as a percentage of the contract value, often with a maximum. Under the UAE Civil Transactions Law a court may adjust agreed compensation so that it equals the actual loss, so the contract figure is not always the final amount. Take legal advice on any claim.

Questions

Does an extension of time reduce liquidated damages?

Yes. Days covered by an extension of time granted under the contract are not charged. The calculator deducts the days you enter.

Can a UAE court change the agreed amount?

Yes. Article 390 of the UAE Civil Transactions Law lets a judge, at the request of either party, adjust agreed compensation to equal the actual loss.

What if the damages pass the cap?

The damages stop at the cap. The calculator shows the capped amount and how many days of delay reach it.