For contractors, consultants and QS in Dubai, Sharjah, Abu Dhabi and Ajman. Enter the original contract sum and the total additions and omissions in AED, and get the net and gross variation as a percentage of the contract, the revised contract sum and a check against a limit in your contract.
Worked example
With the calculator’s starting values:
| Original contract sum | 2,000,000 AED |
|---|---|
| Additions | 180,000 AED |
| Omissions | 60,000 AED |
| Pending variations | 0 AED |
| Limit to check against | 15 % |
| Check the limit on | Net change |
| Net variation | 6 % of contract |
|---|---|
| Net variation amount | 120,000 AED |
| Revised contract sum | 2,120,000 AED |
| Gross variation | 12 % of contract |
| Limit check | Within 15% (net) |
How it is calculated
Net variation = additions − omissions
Net variation % = net variation ÷ original contract sum × 100
Gross variation % = (additions + omissions) ÷ original contract sum × 100
Revised contract sum = original contract sum + net variation
With pending = revised contract sum + pending variations
With the starting values, the net variation is 180,000 − 60,000 = 120,000 AED, which is 6% of the 2,000,000 AED contract. The gross variation is 240,000 AED, or 12%, and the revised contract sum is 2,120,000 AED.
Net or gross
The net figure shows how much the contract sum has moved. The gross figure shows how much work has changed, because additions and omissions do not cancel out in the work. Some contracts set a limit on one or the other, so check which one yours uses.
Defaults you can change
The 15% limit is only an example to show the check. Use the figure in your contract, or enter 0 to skip the check.
Variations in the UAE
On projects in Dubai, Sharjah, Abu Dhabi and Ajman, variations are normally instructed in writing by the engineer or employer and valued under the contract, often a FIDIC-based form. Track additions, omissions and pending claims in AED before VAT, and check the result against the conditions of contract and the consultant’s records.
Questions
Should variations include VAT?
Work in amounts before VAT, the same basis as the contract sum, so the percentages compare like with like.
How do I enter an omission?
Enter it as a positive amount in Omissions. The calculator subtracts it from the additions.
What are pending variations?
Variations submitted but not yet agreed. Enter their net value to see the possible revised contract sum.